Construction of ropeways
A brief look at the construction process

How a ropeway is built

From the initial idea through to the commissioning of a ropeway, numerous planning steps, technical decisions and precisely coordinated workflows are required. Each installation is individually tailored to the requirements of the project and consists of four main components: stations, line, vehicles and parking.

As early as the tender phase, the customer’s general conditions and requirements are analysed in order to develop customised solutions together with the experts at LEITNER. Once the order has been placed, an interdisciplinary project team takes over the subsequent implementation. Technical planning is followed by approval procedures, production, logistics and the construction and assembly work on site.

The following overview shows the key steps from the project idea to the completed ropeway.

Insights into everyday construction work

The installation of the towers in the Patrullarve project
  1. Phase A

    Surveying and foundations

    Topographical, geological and geotechnical check: During the topographical survey, the terrain is measured and then represented graphically. As part of the geotechnical and geological check, the composition and structure of the terrain are examined. These calculations are very important for the correct project engineering of the installation.


    Setting out: This process is important for marking reference points on the ground for the following steps (excavation and reinforced concrete works).


    Excavation: Depending on the stability of the ground on which the installations are built, different equipment is used for excavation, such as heavy excavators for large excavations or spider excavators for terrain that is difficult to access.


    Reinforced concrete works: The basic structures, such as the station and tower foundations, service rooms and station buildings, are built partly or entirely from reinforced concrete.
    At the same time, the availability of standard installation elements, such as roller batteries or supporting structures for the stations, is checked. During this period, mechanical and electrical project engineering, production and the procurement of specific elements of the installation, such as the motor, rope or towers, also begin so that all the components required for assembly are ultimately ready.

  2. Phase B

    Transport and logistics

    The individual components are sent to the building site. If the installations are transported overseas, the components are transported, for example, in containers on ships.

  3. Phase C

    Assembly

    Assembly of the steel components: The steel components are designed as modular assemblies and are pre-assembled in the workshop to speed up and simplify assembly on site. Machines and equipment suitable for the ground conditions are used for assembly, allowing work to be carried out even on difficult terrain. If the terrain is very hard to access, a helicopter or a material ropeway is used, for example, to assemble installation components such as towers and stations. Using a helicopter is a major challenge, as the work has to be carried out very precisely and quickly.


    Mechanical equipment and covering: The brakes, electric motor and gearbox, hydraulic cylinder and other components are installed. The coverings are then fitted on the station.

    Rope assembly: Once the assembly of the elements mentioned above is complete, the wire rope hoist begins. Rope assembly is completed with rope splicing. The assembly of the rope is certainly the most interesting and characteristic part of building a ropeway, but also the most difficult. It is carried out by specialised companies.


    Electrical wiring: The electrical engineers connect the electrical control and monitoring system to the electric motor and all other safety devices in the stations and towers.


    Vehicle assembly: The vehicles are attached to the grips and suspended from the rope or placed in the parking facility.

  4. Phase D

    Commissioning and acceptance

    Adjustment of the mechanics and electrical commissioning: Once assembly has been completed, the mechanical adjustments are carried out and the electrical calibration is performed by specialised technicians.


    Internal checks and technical acceptance: Together with other technicians, the project engineer carries out the functional tests on the various components of the installation. The checks are then performed in the presence of the inspection authorities, who verify that everything complies with the statutory and country-specific requirements.

A milestone in the construction phase

Insights into the art of rope splicing